Nuclear power plants in Germany

Shutting down reactors that are still in operation in accordance with the German Atomic Energy Act AtG)

AKW Abschaltung_EN Gundremmingen C Gundremmingen B Isar 2 Neckarwestheim 2 Philippsburg 2 Grohnde Emsland Brokdorf

Overview of German nuclear power plants

Grafenrheinfeld nuclear power plant was shut down on 27 June 2015, meaning that there are only eight operational nuclear power plants left in Germany. As stipulated in the German Atomic Energy Act, the three newest reactors will be shut down in 2022, with the others shutting down in 2017, 2019 and 2021 at the latest.

Gundremmingen, Block B (KRB II B) - Bavaria
Type (construction line): BWR (72) | Gross capacity: 1,344 MWe
Application date: 15 March 1974 |
Commissioning (first criticality): 9 March 1984 |
Commercial operation: 19 July 1984
Expiry of authorisation for power operation in accordance with the German Atomic Energy Act (AtG): 31 December 2017
State supervisory authority

Philippsburg 2 (KKP 2) - Baden-Württemberg
Type (construction line): PWR (3 | Pre-Konvoi) | Gross capacity: 1,458 MWe
Application date: 24 June 1975 |
Commissioning (first criticality):13 December 1984 |
Commercial operation: 18 April 1985
Expiry of authorisation for power operation in accordance with the German Atomic Energy Act (AtG): 31 December 2019
State supervisory authority

Grohnde (KWG) - Lower Saxony
Type (construction line): PWR (3 | Pre-Konvoi) | Gross capacity: 1,430 MWe
Application date: 3 December 1973 |
Commissioning (first criticality): 1 September 1984 |
Commercial operation: 1 February 1985
Expiry of authorisation for power operation in accordance with the German Atomic Energy Act (AtG): 31 December 2021
State supervisory authority

Gundremmingen, Block C (KRB II C) -  Bavaria
Type (construction line): BWR (72) | Gross capacity: 1,344 MWe
Application date: 15 March 1974 |
Commissioning (first criticality): 26 October 1984 |
Commercial operation: 18 January 1985
Expiry of authorisation for power operation in accordance with the German Atomic Energy Act (AtG): 31 December 2021
State supervisory authority

Brokdorf (KBR) - Schleswig-Holstein
Type (construction line): PWR (3 | Pre-Konvoi) | Gross capacity: 1,480 MWe
Application date: 12 March 1974 |
Commissioning (first criticality): 8 October 1986 |
Commercial operation: 22 December 1986
Expiry of authorisation for power operation in accordance with the German Atomic Energy Act (AtG): 31 December 2021
State supervisory authority

Isar 2 (KKI 2) - Bavaria
Type (construction line): PWR (4 | Konvoi) | Gross capacity: 1,485 MWe
Application date: 13 February 1979 |
Commissioning (first criticality): 15 January 1988 |
Commercial operation: 9 April 1988
Expiry of authorisation for power operation in accordance with the German Atomic Energy Act (AtG): 31 December 2022
State supervisory authority

Emsland (KKE) - Lower Saxony
Type (construction line): PWR (4 | Konvoi) | Gross capacity: 1,400 MWe
Application date: 28 November 1980 |
Commissioning (first criticality): 14 April 1988 |
Commercial operation: 20 June 1988
Expiry of authorisation for power operation in accordance with the German Atomic Energy Act (AtG): 31 December 2022
State supervisory authority

Neckarwestheim 2 (GKN 2) -  Baden-Württemberg
Type (construction line): PWR (4 | Konvoi) | Gross capacity: 1,400 MWe
Application date: 27 November 1980 |
Commissioning (first criticality): 29 December 1988 |
Commercial operation: 15 April 1989
Expiry of authorisation for power operation in accordance with the German Atomic Energy Act (AtG): 31 December 2022
State supervisory authority